January 16, 2026 – Construction Progress Update

Men’s & Ladies’ Washrooms Removed – AGH Banquet Room Front Foyer

Future Location for Banquet Crush Reception Bar, Banquet Washrooms & Banquet Prep Kitchen Fireplace Shown – to be removed

AGH Banquet Room Demolition Progress Steel Pillars to be Removed Spring 2026 Boardroom to begin demolition early February 2026

Member’s Lounge Washrooms Framed, ready for Plumbing & Drywall

Patio Rotunda Roof Ready for Steel Canopy Extensions to be installed in February 2026

Elevator Pit Basement Excavation Under Main Corridor Stairs

No Access to Stairs Starting Mid-February 2026 Main Corridor Ramp will be Exclusive Access for Curlers/Members Elevator Shaft to be Installed

No Access to Former Curling Lounge Starting March 1, 2026 Construction Team Requires Access to Complete Restaurant Area

Temporary Curling Lounge will Remain Accessible through until end of Curling Season 2026